hi mike

typical mark up is 3x cost
1=cost
1=overhead
1=profit

i bid on a huge job a while back, and
i was asked to state in the estimate
hard (direct) and soft(indirect) costs, and what percentage
of the total job my profit was to be ....

it was a brutal estimate ...